Next Workday
Workdays are the 1st Saturday and 3rd Sunday of the month.
The next workday will be Saturday the 3trd of March from 8am at Garratt Central(Canberra Railway Museum). New volunteers are always welcome, no skills are required, just a willingness to get dirty.
Fundraising Appeal
Finally I can announce that people who donate over $500 in total to Project6029, will qualify for a cab ride once 6029 is back in service. What an incentive! Anyone can qualify for this bonus, and those that have already donated are in the running. Just donate a total of $500 or more and you are in the queue...
Jul 20, 2011
Sunday 17 July 2011
Andy continued with the fitting out of the large bore injector feed pipes and by days end all of the drives side was completed and looking like new. Tony cleaned up the water balance pipe isolating vale and associated fittings. The only outstanding large bore pipe on the drivers side pipe is the feed lines from the injector to the clack vales on the top of the boiler.
The stoker trough that is attached under the coal bunker is in very poor condition and will required a complete rebuild. Most of the afternoon was dedicated to extracting the 24 one inch BSW bolts that attach the front of the stoker trough to the coal bunker. No amount of force would remove them so the oxy torch was deployed and about two hours later the team tried to drop out the assembly. Despite our best efforts it resisted and with the fading light, it was decided to make a tactical retreat and leave it until the next work day.
Another project going on behind the scenes is the overhaul of the Westinghouse cross compound air compressor. It was stripped down and assessed in 2009 and although in reasonable condition it was decided to give this vital piece of equipment the gold plate(aka Rolls Royce) treatment. Since then, the piston rods have been hard chromed and ground to size. The cylinder assembly and shuttle valve head were sent to a specialist contractor and line bored back to specification, and a complete set of piston rings was recently delivered and fitted with excellent results. The pistons now move up and down the bores with a good running seal.
New gaskets have been ordered and when delivered they will be fitted in no time. That will leave only an air function test before fitting the complete unit to the smoke box.
Alan Gardner
How can you help 6029 get back on the rails?
This project is self funded, the workers are all volunteers, and we need your help.
Maybe you can come to Canberra on a work day and get your hands dirty, or you have a nice workshop at home and need a reason to spend more time in it.
Maybe you can't make it to Canberra, but could do a little work in Sydney, if you think you have something to offer, contact us...even if you don't think you have anything to offer, but want to be involved in preserving a litlte piece of history, contact us and we will do our best to find something interesting and productive to suit you.
Even the simplest things can help...can you spare $5 or $10 a week? it's small change on its own, but if 20 people could donate $10 a week, that would be $800 a month that we don't have now, and every dollar will help us put this monster back on the rails for everyone to enjoy.